Milestones that are drifting, spotted early
by AGNTOfficialAgent template
Each week an agent compares the milestone dates in your plan with how the work behind them is actually moving, projects where each milestone will really land, and posts the ones drifting — with the cause — while there is still time to act.
Opens in AGNT and takes about a minute.
Didn’t open? AGNT may not be installed here yet. Download AGNT free · Download the .json
- 3
- Tools connected
- ~10 min
- Setup, 4 steps
- Local
- Runs on your machine
- Per category
- You approve
- Any model
- Uses the one you have
What the agent actually does
Projected dates, not hoped-for ones
For each milestone the agent projects a landing date from the pace of the last few weeks, and shows it next to the planned date.
The cause, where the data shows it
Drift usually has a visible cause: tasks added after planning, a blocked dependency, an owner with too much work. The post names it when the data shows it.
Early enough to matter
A milestone two weeks behind with six weeks to go can be rescued. The same milestone discovered the week before is a missed date. The weekly check exists to buy that time.
The tools this job needs
Notion
Where the work arrives. The team wiki agents can actually keep current. The agent watches it and reads what turns up in full, rather than matching a rule against a subject line.
Google Sheets
Context the agent pulls in before deciding. The database every team already has open. It is read, not just referenced — which is what lets the decision account for it.
Slack
Where the result lands. Team chat where operations actually surface. Nothing is written here until the agent has formed a view and, where you asked for it, you have approved it.
The brief it works from
This is the actual instruction set the template installs — what the agent is told to do, and what it is told never to do. Every line of it is yours to edit in AGNT after install.
Read the full brief
You spot milestones that are drifting while there is still time to act.
Read
The plan sheet: milestone, planned date, owner, and the Notion task database and milestone property or tag for its tasks. Query the tasks: status, created date, completed date if available.
Measure
For each milestone: tasks total, done, remaining; tasks added since the plan date (scope growth); completion rate per week over the last four weeks (or as many as exist). Projected date = today + remaining / weekly rate. If the rate is zero, the projection is "no recent progress".
Compare
Drifting = projected date later than the planned date by more than the user’s tolerance (default seven days). For drifting milestones, look for causes: scope growth, tasks marked blocked, many open tasks with one owner.
Post
Post to Slack: drifting milestones first, each with planned and projected dates, the numbers behind the projection and the likely cause; then milestones on track in one line each.
Boundaries
Never change dates, tasks or the plan sheet. Always label projections as estimates with their basis. Never attribute drift to a person’s performance; report workload as numbers.
Shown exactly as it ships. The agent inherits whichever model you already use.
Plans are optimistic by design
Every plan is made with incomplete information, so dates drift as reality arrives: scope grows, estimates were short, a dependency is late. Drift itself is normal. The problem is noticing it late, when the only options left are cutting scope in a hurry or missing the date. A weekly comparison of plan with progress makes drift visible while there are still good choices available.
Pace is the signal
A milestone with half its tasks done is on track or not depending on how fast tasks have been completed recently and how many remain. The agent measures the completion rate over the last few weeks, projects the remaining work forward, and compares the projected date with the plan. It also tracks scope growth, because tasks added after planning are the most common cause of drift and the easiest to discuss.
A projection, clearly labelled
Projections are estimates, not promises, and the post says so: each projected date comes with the pace and remaining work it was based on. Teams can disagree with a projection, and when they do, the conversation is about specific numbers. The agent never moves dates in the plan; that decision belongs to the people who own it.
Common questions
Does it change the plan?
No. It projects and reports. Moving dates or cutting scope is your decision.
How many weeks of history does it need?
Two weeks gives a rough projection; four or more gives a steadier one.
What if tasks are not estimated?
It projects from the number of tasks completed per week. Estimates, if present, make the projection better.
Can it include GitHub issues?
This template reads Notion tasks. For GitHub-based work, the project status roll-up uses milestones directly.
What counts as drifting?
A projected date later than the planned date by more than your tolerance, one week by default.